Here are the photo's of the finished results of the refurbishment arena at Mill Field School Somerset.
The levels of the formation we corrected and compacted. The drainage was replaced with new trenching with a geotextile laid over to prevent contamination.
A perforated pipework network was installed with a clean drainage stone over to the correct depths and levels then compacted.
The fencing was then installed with round posts, T&G kick boards, three rails up and one gateway leaving gaps around for the mirror reinstallation when completed.
A heavy duty Equestrian geotextile was laid over the stone to prevent the ingress of sand into the draianage layer which had all seams glued and fixed to the kick boards.
A top of the range Wax Sand and Fibre surface was then laid to the correct depths and compacted.



